Cranes are set up and ready for girders. Girders have arrived on site. First one being set into place. On the third girder. 5 total delivered today. Setting the final one for the day. 5 completed. Remaining will be delivered next week.
View of bridge from end bent 1. Wing wall on end bent 1. Shaping road between end bent 4 and box culvert. View of bridge from end bent 4. Backfill material being hauled in throughout the day. Rebar tied this morning for approach. View from the top of the bridge looking toward end bent 4.
Realm Construction is in today tying rebar for the box culvert. Working on getting the walls set. Interior forms are nearly complete. Hartman crew working on this. Dirt work on west side of the project. View from the south. Creek edge has been adjusted.