Cranes are set up and ready for girders. Girders have arrived on site. First one being set into place. On the third girder. 5 total delivered today. Setting the final one for the day. 5 completed. Remaining will be delivered next week.
Equipment delivery. Finishing up removing the forms from the box culvert. Work slab in around the piling for end bent 4. CMP delivered. Work slab in around the piling for end bent 1.
Concrete pour for the box culvert walls. Working on finishing up the pour. Rock delivered and being compacted on the west side of the project. Overall view from the south.