Girders have arrived. 6 are set with 3 left to do. Ticket off one of the girders. Getting set in place between bent 1 and bent 2. Girders are all set and look great.
Cranes are set up and ready for girders. Girders have arrived on site. First one being set into place. On the third girder. 5 total delivered today. Setting the final one for the day. 5 completed. Remaining will be delivered next week.
Continuing to work on the new road near end bent 1. We have got the road built up. Getting closer to finished elevation. Continuing to cut where needed. View of the road from the south end of the project. Continued.. View of the road from end bent 1. You can see how much we’ve come up from the previous elevation.