Round Mountain Bridge - 5/3/2021
View of project from the south.
Getting drainage pipes re-installed to get the temporary crossing back in. Damaged from flooding. Had to re-do.
Box culvert top nearly ready for rebar. Ironworkers scheduled for tomorrow. Concrete set for Wednesday afternoon.
Pipes are in. Guys working on getting everything covered back up so we can open the temporary crossing again.
Arrow Drilling has brought out there equipment for the two intermediate bents. CMT was out setting new pins for them to go of off.