Cranes are set up and ready for girders. Girders have arrived on site. First one being set into place. On the third girder. 5 total delivered today. Setting the final one for the day. 5 completed. Remaining will be delivered next week.
Realm Construction is in today tying rebar for the box culvert. Working on getting the walls set. Interior forms are nearly complete. Hartman crew working on this. Dirt work on west side of the project. View from the south. Creek edge has been adjusted.
North side of the box culvert has the rebar complete. Will begin setting forms up. South side rebar is being installed by Realm Construction. Tearing out the existing crossing. A lot of busted up concrete being hauled off. Forms being set up as the rebar install is complete.