Posts

Round Mountain Bridge - 6/10/2021

Image
Bridge alignment from the west side of the creek. Removed forms from bent 3 cap. Getting ready for girders to be delivered next week.

Round Mountain Bridge - 6/9/2021

Image
Grading around bent 2. Concrete pour for bent 3 cap.

Round Mountain Bridge - 6/8/2021

Image
Rip rap on end bent 1. Getting cap ready on bent 3. Pour set for tomorrow. Rip rap being installed on end bent 4.

Round Mountain Bridge - 5/19/2021

Image
Lowering the form around the piling/rebar for bent 2. Rebar being put together for bent 3. Bent 2 is ready for concrete. Pour tomorrow at 10:30.

Round Mountain Bridge - 5/18/2021

Image
Dug out around the pilings for bent 2. Concrete poured around the bases of the pilings. Pour is complete.

Round Mountain Bridge - 5/14/2021

Image
Driving piling for bent 3 today. Second one is complete. Three left to do. All the piling is in and bent 3 is finished. View of the project from the south.

Round Mountain Bridge - 5/13/2021

Image
Getting the hammer set up on the crane. Driving piling for bent 2 today. Getting the first piling lined up. About half way through the process. All piling is in and we’re ready to remove the hammer.