Round Mountain Bridge - 5/19/2021

Image
Lowering the form around the piling/rebar for bent 2. Rebar being put together for bent 3. Bent 2 is ready for concrete. Pour tomorrow at 10:30.

Round Mountain Bridge - 5/18/2021

Image
Dug out around the pilings for bent 2. Concrete poured around the bases of the pilings. Pour is complete.

Round Mountain Bridge - 5/14/2021

Image
Driving piling for bent 3 today. Second one is complete. Three left to do. All the piling is in and bent 3 is finished. View of the project from the south.

Round Mountain Bridge - 5/13/2021

Image
Getting the hammer set up on the crane. Driving piling for bent 2 today. Getting the first piling lined up. About half way through the process. All piling is in and we’re ready to remove the hammer.

Round Mountain Bridge - 5/12/2021

Image
End bent 4 ready for concrete. Temporary crossing is back up and running. Concrete pour underway. Smoothing out the concrete.

Round Mountain Bridge - 5/11/2021

Image
Current state of the job site. Temporary crossing being put back in. Forms removed from end bent 1.

Round Mountain Bridge - 5/10/2021

Image
High waters over the weekend tore out our temporary crossing for the second time. End bent 1 is ready for concrete. Concrete pour has begun. Pour is over. Getting things smoothed out.

Round Mountain Bridge - 5/7/2021

Image
Forms removed from south side of box culvert. Forms removed from north side of box culvert. Pre-bore for bent 2. End bent 4 is ready for concrete.

Round Mountain Bridge - 5/6/2021

Image
Crew working on getting the forms set on end bent 4. Arrow Drilling on site drilling for bent 2. Overall view of the project from the south.

Round Mountain Bridge - 5/5/2021

Image
Wrapping up rebar work on end bent 4. Drilling for bent 3. Concrete pour for box culvert top. Rebar work on end bent 1. Smoothing out the surface of the new concrete on the box culvert.