Round Mountain Bridge - 8/26/2021

Image
Removing temporary crossing. View of the guardrail from end bent 4. Guardrail crew wrapping up their install on the north end.

Round Mountain Bridge - 8/25/2021

Image
Guardrail crew getting install done on end bent 1. Temporary crossing being removed. View of the bridge from the deck. Grading on north end of the project.

Round Mountain Bridge - 8/24/2021

Image
View of the bridge from end bent 1. Riprap along west end of Goodnight Hollow. Grading down around the creek. Guardrail crew working on end bent 4. Access drive for property owner in. Fence and gate marked out. Grading complete on north end of project. Rip rap on east side of Goodnight Hollow. West side of Goodnight Hollow. Guardrail going in on end bent 1.

Round Mountain Bridge - 8/23/2021

Image
Grading on the south end of the job. View of the project from near end bent 1. Guardrail crew is in and materials delivered. Getting riprap installed on Goodnight Hollow. Guardrail crew is underway on the bridge.

Round Mountain Bridge - 8/20/2021

Image
Crew is working on getting rip rap installed on Goodnight Hollow. Blankets are down. View of the riprap from the east. View of the project from end bent 4. Created a access for the property owner to be able to reach his land down near end bent 4.

Round Mountain Bridge - 8/19/2021

Image
View of the road from up Round Mountain Road. Goodnight Hollow road built up. Rip rap installed on edge of Goodnight Hollow. Working on the second half of the rip rap. Installed a temporary radius for a school bus to make the turn next week until our guard rail is installed.